Carnbane Bridge 2, Newry

This project involved the construction of a 19.5m single span bridge across the Newry River at Carnbane Industrial Estate, Newry, The bridge deck consisted of M6 precast prestressed concrete beams with an in-situ, reinforced concrete deck slab complete with parapet upstands and N2 vehicular Parapet Railings.The deck was supported on reinforced concrete abutments with wing walls, with the abutments supported on 18m long precast concrete driven piles.

Associated works included:

  • Construction of new 80m long access road complete with tie-in to existing industrial estate service road
  • Footway construction
  • Safety Fencing & Parapet railings
  • Services
  • Drainage
  • Street Lighting
  • Landscaping
  • Safety Fencing & Parapet railing