This project comprised the construction of flood alleviation measures along the Kilkeel River adjacent to existing factory units, including the construction of a Steel Sheet Piled wall and in-situ concrete retaining wall to provide future river flood protection, dredging of the river bed and the supply and placing of rock armour.
Works included:
- Site Clearance
- Earthworks, including dredging of river bed
- Steel Sheet Piling, complete with in-situ concrete pile cap
- In-situ concrete flood protection wall, complete with associated stop logs
- Security Fencing
- Services
- Drainage
- Rock Armour